MULTIS 400+
Leeds • CLEGG Construction
Grade A
Office Block.
Structural formwork | 2026
Background
MULTIS 400+ Used in £60m Landmark Leeds Office Development
MULTIS 400+ reinforced PVC formwork boards are being used in the construction of a prestigious £60 million Grade A office development in the heart of Leeds. Delivered by Clegg Construction, the nine-storey, 80,000 sq ft building is scheduled for completion in summer 2027.
For the construction of the lift shaft and two stairwell cores, 19 mm MULTIS 400+ boards have been incorporated into the PERI TRIO formwork system to produce a plain concrete finish. The project demonstrates the application of MULTIS 400+ within an established formwork system on a major commercial development.
MULTIS 400+ in PERI TRIO panel system
Pour 1 finish
Pour 1 joint
MULTIS 400+ in situ
Core 1 inner walls constructed with MULTIS 400+
MULTIS 400+ IN ACTIONFormwork application
Key specifications behind the application
Application
Lift shaft and two stairwell cores
Panel System
PERI TRIO
Board Thickness
19 mm
Finish
Plain Finish
“It’s delivered the finish we needed, worked with our existing formwork and is a product we’d certainly consider using again.”
— Chris Henessey, Senior Site Manager, Clegg Construction